Group Meetings:

  • DIGM development meeting   (2 hrs)
  • CS development meeting  (2 hrs)
  • Full team design meeting (2 hrs)
  • EGS/Production Schedule meeting (2 hrs)

Production Work:

  • Website setup   (3 hrs)
  • Visuals first production draft (3 hrs)
  • Map design first production draft (3 hrs)
  • CS development (6 hrs)

 

 

Positive:

  • Visuals coming along nicely.
  • Prototypes functioning at expected levels.
  • We have a website now. (This is that website.)

Negative:

  • Took longer than expected to finish settling production schedules.

Total Hours for the week: 23

 